Recyco
Project Description
Struct Steel Engineering were appointed by Recyco to provide the connection design, supply and erect the structural steel, supply and install all precast walling and supply and install all wall and roof cladding for Recyco’s new double portal frame production facility building.
Struct Steel Engineering worked closely with Recyco’s groundworks contractor to ensure accurate setting out of the double portal frame.
Struct Steel Engineering continually liaised with Recyco to ensure the timing of delivery of specialist equipment which required elements of the work to be fast tracked or delivery programs to be adjusted to meet their requirements.
- Steel connection design
- Detailing, fabrication & erection of Structural Steelwork
- Supply & Installation of 8800 SQ/M of internal & external insulated cladding. Including all flashings & trims
- Detail, supply & fit all precast walls
Client: Recyco
Project Type: New Manufacturing Facility
Steel Tonnage: 225T
Project Location: Omagh, N Ireland